1. (TCO 4) Compare and contrast top-down and bottom-up project estimating technique
| Question 1. 1. (TCO 4) Compare and contrast top-down and bottom-up project estimating techniques. (Points : 20) |
| Question 2. 2. (TCO 6) You are comparing two projects. Using the data below, calculate the CV, SV, SPI, and CPI. Second, use the values to provide the status of each project. All values are in dollars. Project AProject BEV650550PV750575AC675525(Points : 20) |
| Question 3. 3. (TCOs 4 and 6) Describe the 4-step general model of project control. Provide examples of each step. (Points : 20) |
| Question 4. 4. (TCO 8) All projects suffer from some form of conflict at one time or another. List and describe four common sources of conflict on a project and provide examples of each from either a recent project or from your personal life. (Points : 20) |
| Question 5. |