In the Needs Phase of the Project Life Cycle, you’ve hit a road block! Two key people on the customer’s team have

a disagreement about requirements. Precious project time is slipping away. As Project Manager, what is probably your best approach?

a.    Inform the project sponsor that there is a disagreement and the project will most likely slip

b.    Ask the project sponsor to assign a more seasoned Project Manager

c.    Try to get one of the disagreeing individuals removed from the project

d.    Arrange a meeting in which you can attempt to facilitate agreement

In the Needs Phase of the Project Life Cycle, you’ve hit a road block! Two key people on the customer’s team have

a disagreement about requirements. Precious project time is slipping away. As Project Manager, what is probably your best approach?

a.    Inform the project sponsor that there is a disagreement and the project will most likely slip

b.    Ask the project sponsor to assign a more seasoned Project Manager

c.    Try to get one of the disagreeing individuals removed from the project

d.    Arrange a meeting in which you can attempt to facilitate agreement

 