Aco completes job#101 which has a standard of 600 labor hours at a standard rate of $20.00 per hour.
GivenAco completes job#101 which has a standard of 600 labor hours at a standard rate of $20.00 per hour.
The job was completed in 500 hours and the average actual labor was $18.75 per hour.
Determine
What is the labor efficiency variance?