Best writers. Best papers. Let professionals take care of your academic papers

Order a similar paper and get 15% discount on your first order with us
Use the following coupon "FIRST15"
ORDER NOW

An assembly line with 17 tasks is to be balanced

Question

An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all

tasks is 18 minutes. The line will operate for 450 minutes per day.

a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)

  Minimum cycle time ____minutes

Maximum cycle time _____minutes 

b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the smaller value in the first box and the larger value in the second box.)

Range of output  ___ to___    units/day

c. What is the minimum number of workstations needed if the maximum output rate is to be sought? (Round up your answer to the next whole number.)

Minimum number of workstations           

d. What cycle time will provide an output rate of 125 units per day? (Round your answer to 1 decimal place.)

Cycle time      ______  min/cycle

e. What output potential will result if the cycle time is (1) 9 minutes? (2) 15 minutes?

Cycle Time Potential Output

(1) ____ ____Units

(2) ____ ____units

 
Looking for a Similar Assignment? Order now and Get 10% Discount! Use Coupon Code "Newclient"