CO 3) James Company uses process costing to track its costs
CO 3) James Company uses process costing to track its costs in two sequential production departments: Forming and
Finishing. The following information is provided regarding the Forming Department:
Forming Department
Month Ended June 30
Unit information
Beginning work in process, June 1 — 4,000
Started into production during June — 22,000
Completed and transferred to Finished Department during June — 20,000
Ending work in process, June 30 (20% complete as to direct materials and 50% complete as to conversion costs) — 6,000
Cost information:
Beginning work in process as of June 1 consists of $1,000 of direct materials costs and $4,500 of conversion costs — $5,500
Direct materials used in June — $7,268
Conversion costs incurred in June — $32,990
Required:
(a) Calculate the equivalent units for direct materials. (Show your work)
(b) Calculate the cost per equivalent unit for direct materials. (Show your work) (Points : 30)