Direct materials $10,500 This question was created from ex 17-13
Answer:
Total applied overhead = 36,894
Overhead rate using Job 301 data:
Overhead rate = overhead / direct labor cost = 4752 / 7200 = 0.66 of direct labor cost
So,
Job 301 = 4,752 (given)
Job 302 = 10,296 (given)
Job 303 = 0.66 x 19,100 = 12,606
Job 304 = 0.66 x 14,000 = 9,240
Total applied overhead = 36,894