Question A 2200-MWe advanced nuclear plant has an expected construction cost of $5,000/kWe and estimated annual O&M expenses of $89/kWe. If the projected fuel charge is $2/(MWe h), compute the electricity generation cost for an annual levelized fixed charge rate of 15% and anticipated capacity factor of 92%.
Question
A 2200-MWe advanced nuclear plant has an expected construction cost of $5,000/kWe andestimated annual
O&M expenses of $89/kWe. If the projected fuel charge is $2/(MWe h),
compute the electricity generation cost for an annual levelized fixed charge rate of 15% and
anticipated capacity factor of 92%.