The following are the cash flows of two projects
Question
1) The following are the cash flows of two projects: Year Project A Project B0 (310)
(310)
1 140 210
2 140 210
3 140 210
4 140
a. If the opportunity cost of capital is 10%, calculate the NPV for both projects. (Do not round intermediate calculations. Round your answers to 2 decimal places.)
Division a
Division b
2)
The following are the cash flows of two projects:
Year Project A Project B
0 (270) (270)
1 150 170
2 150 170
3 150 170
4 150
a. Calculate the NPV for both projects if the discount rate is 12%. (Do not round intermediate calculations. Round your answers to 2 decimal places.)
Project A
Project b
4)
The following are the cash flows of two projects:
Year Project A Project B
0 – 220 -220
1 100 120
2 100 120
3 100 120
4 100
What is the payback period of each project in years? (Round your answers to 1 decimal place.)
Project A
Project B
5)
A project that costs $4,150 to install will provide annual cash flows of $1,400 for each of the next 6 years.
a. What is NPV if the discount rate is 15%? (Do not round intermediate calculations. Round your answer to 2 decimal places.)
b. How high can the discount rate be before you would reject the project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places.)