1. Complete the network diagram by conducting a forward and backward pass through
1. Complete the network diagram by conducting a forward and backward pass through the
network. Compute the early/late start time, early/late finish time, and slack time for each activity
2. What is the project duration?
3. What is the critical path of this network?
4. Using any approach you wish (e.g., trial and error) develop a loading chart for the project resources: Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available.
5. Using the resource loading chart, now compute the early/late start time, early/late finish time, and slack time for your project. Illustrate this new resource constrained network in a network diagram.
6. Complete the resource activity schedule.
7. For the new network, what is the new project duration?
8. Which activities are now critical?
ATTACHMENT PREVIEW Download attachment
PMAN634Session 9 – Individual AssignmentSession 9 IA-9(1)Given this network plan, complete the following activities:1.Complete the network diagram by conducting a forward and backward pass through thenetwork. Compute the early/late start time, early/late finish time, and slack time for eachactivity2.What is the project duration?3.What is the critical path of this network?4.Using any approach you wish (e.g., trial and error) develop a loading chart for the projectresources: Carpenters (C) and Electricians (E).Assume only one Carpenter is available andtwo Electricians are available.5.Using the resource loading chart, now compute the early/late start time, early/late finishtime, and slack time for your project.Illustrate this new resource constrained network in anetwork diagram.6.Complete the resource activity schedule.7.For the new network, what is the new project duration?8.Which activities are now critical?
Background image of page 1
Step-
Looking for a Similar Assignment? Order now and Get 10% Discount! Use Coupon Code "Newclient"