13.1) Given the diagram shown in Figure EX. 13.1, with activites A through G and duration times.
13.1) Given the diagram shown in Figure EX. 13.1, with activites A through G and duration times. A) identify the
paths and path duration times. B) Determine the critical path.
13.3 ES, LS, EF, LF AND Slack time for the activities in excercise 13.1
A hospital is planning to add a $60 million patient tower. In order to support both the existing hospital facility and the new patient tower, an existing energy plant willbe expanded and upgarded. Equipment upgrades include a new gerenator, liquid oxygen tanks, cooling towers, boilers and chiller system to ensure adequate electricity, heating, are conditioning, hot water and oxygen delivery system. Existing fuel tanks wil be relocated. The activities, their immediate predecessors, and the optimistic, most likely and pessimistic times in weeks for the project are listed in Table EX 13.11