A project has an initial outlay of $1,790. It has a single payoff at the end of year 10 of $7,182. What is the net present value (NPV) of the project if the company’s cost of capital is 13.02 percent? Round the answer to two decimal places.
A project has an initial outlay of $1,790. It has a single payoff
at the end of year 10 of $7,182. What is the net present value (NPV) of the project if the company’s cost of capital is 13.02 percent?
Round the answer to two decimal places.