14) Assume you are risk-averse and have the following three choices. Expected ValueStandard DeviationA$2,520 $1,420 B 2,930 1,050 C 2,480 1,040 a.Compute the coefficient of variation for each. (Round your answers to 3 decimal places.) ProjectsCoefficient of VariationA B C b.Which project will you select? Project CProject AProject B