The following table contains information about five jobs waiting to be processed at work
center number three.
Job Processing Time (hrs) Hours Until Due
a 14 15
b 10 20
c 18 18
d 2 16
e 4 21
The sequence that would result using the SPT rule is:
e-b-c-d-a.
c-a-b-e-d.
a-d-c-e-b.
d-e-b-a-c.
e-d-b-a-c.