Hello, I hope you are doing well.
Hello, I hope you are doing well. I need your help in Unit 9 (Resourcing Project/Resource Leveling) for PMGT 510. Please see the image. I am trying to find the answer of question (b). The question asks how many days will it take for the project to get completed. The answer shows 26 days. For this case, I am assuming that B-D-E-G-I path is taken for calculation but I am confused why they have chosen this path? Why they did not choose the other two?
Question.PNG