project network; compute the early, late, and slack activity times (10 points); determine the planned project duration; and identify the critical path. (10 points) His assistant has collected the following information for the Color Printer Drivers Software.
project network; compute the early, late, and slack activity
times (10 points); determine the planned project duration; and identify the critical path. (10 points) His assistant has collected the following information for the Color Printer Drivers Software. (Total 15 points)
ID Description Predecessor Time
A External specifiation None 8
B Review design features A 2
C Document new features A 3
D Write software A 3
E Program and test B 40
F Edit and publish notes C 2
G Review manual D 2
H Alpha site E,F 20
I Print manual G 10
J Beta site H.I 10
K manufacture J 12
L Release and ship K 3
Looking for a Similar Assignment? Order now and Get 10% Discount! Use Coupon Code "Newclient"
