Suppose you have a project consisting of three activities. Midway through the project you collect the following information:

Suppose you have a project consisting of three activities. Midway
through the project you collect the following information:
Activity
PV
EV
AC
1
30
40
35
2
20
15
15
3
10
10
15

What is the project-level Schedule Variance (SV) and Cost Variance (CV)? What is the project-level Schedule Performance Index (SPI) and Cost Performance Index (CPI)?

 