The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A— 6
B A 3
C A 7
D C 2
E B, D 4
F D 3
G E, F 7
a. What is the critical path?
b. How many weeks will it take to complete the project?
c. How much slack does activity B have?