You are comparing two projects. Using the data below, calculate the CV, SV, SPI, and CPI.
You are comparing two projects. Using the data below, calculate the CV, SV, SPI, and CPI. Second, use the
values to provide the status of each project. All values are in dollars.
Project A Project B
EV 450 550
PC 465 575
AC 425 650