A job has a flow time of 14, takes 3 days to process
A job has a flow time of 14, takes 3 days to process, and is due on day 11. How tardy will it be?.
A job is due on day 1 and has 3 days of processing left. It is currently day 4. What is the critical ratio
A job is due on day 20 and has 4 remaining operations with 8 days of processing left. What is the slack per operation?
Which priority rule results in the lowest average completion time