A producer of inkjet printers is planning to add a new line of printers,

A producer of inkjet printers is planning to add a new line of printers,
and you have been asked to balance the process, given the following task times and precedence relationships. Assume that cycle time is to be the minimum possible.

Task Length(minutes) Immediate Predecessor
a 0.2 –
b 0.4 a
c 0.3 –
d 1.3 b, c
e 0.1 –
f 0.8 e
g 0.3 d, f
h 1.2 g

Enter the number of following tasks for each of the tasks shown in the table below

Task Number of Following Tasks
a.
b
c
d
e
f
g
h

 