A project has an initial outlay of $4,435.
A project has an initial outlay of $4,435. It has a single payoff
at the end of year 2 of $6,271. What is the net present value (NPV) of the project if the company’s cost of capital is 10.02 percent?
Round the answer to two decimal places.