Problem 7-3

A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table.

OBSERVATIONS (minutes per cycle)

ElementPerformance

Rating123456190% 0.44 0.50 0.43 0.45 0.46 0.46 285 1.50 1.52 1.47 1.51 1.49 1.52 3110 0.84 0.89 0.77 0.83 0.83 0.80 4100 1.10 1.14 1.08 1.15 1.16 1.26

a.Determine the average cycle time for each element. (Round your answers to 3 decimal places.)

Element Average cycle 1 2 3 4

b.Find the normal time for each element. (Round your answers to 3 decimal places.)

Element Normal time 1 2 3 4

c.Assuming an allowance factor of 18 percent of job time, compute the standard time for this job. (Round your answers to 3 decimal places.)

Element Standard time 1 2 3 4

Image transcriptions

Problem 7-3 A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. OBSERVATIONS (minutes per cycle) Performance Element Rating 1 2 3 4 5 6 1 90% 0.44 0.50 0.43 0.45 0.46 0.46 2 85 1.50 1.52 1.47 1.51 1.49 1.52 3 110 0.84 0.89 0.77 0.83 0.83 0.80 4 100 1.10

 
Looking for a Similar Assignment? Order now and Get 10% Discount! Use Coupon Code "Newclient"