Compute the NPV statistic for Project U if the appropriate cost
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent.
(Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project U
Time: 0 1 2 3 4 5
Cash flow -$1,300 $470 $1,780 -$580 $420 -$160
NPV$ _______
Should the project be accepted or rejected?
Accepted
Rejected