Greetings, Please show detailed steps on how you arrived to the answer
Greetings, Please show detailed steps on how you arrived to the answer.
Abagail Corp. uses activity-based costing system with three activity cost pools. The following information is provided:
Costs: Wages and salaries $ 212,000
Depreciation 111,000
Utilities 110,000
Total $440,000
Activity Cost Pools
Assembly Setting Up Other
Wages and salaries 0.54 30% 10%
Depreciation 0.34 45% 20%
Utilities 0.28 40% 30%
How much total cost would be allocated to the Assembly activity cost pool?