Reconsider the network diagram. S

Reconsider the network diagram. Suppose that after 12 weeks, activities
1-2, 1-3, and 2-4 have been finished; activity 2-5 is 75 percent finished; and activity 3-6 is half finished. How many weeks after the original start time should the project be finished?

Project can be completed in a total of weeks.

 